What Happens Between Planning Approval and Construction? A Step-by-Step Timeline

Getting planning permission is a milestone, not the finish line. Most projects need another 8 to 16 weeks of legal, technical and practical work before a contractor can start on site.

It depends on your project, but the key determinant is how many conditions your approval carries and how complex the build is. A simple rear extension with few conditions can be ready in under two months. A listed building or large scheme with a long condition list can take considerably longer.

What Happens Between Planning Approval and Construction? A Step-by-Step Timeline

Key Insights at a Glance

  • Planning conditions must usually be formally discharged before development begins, or you risk building unlawfully even with a valid permission.
  • Building Regulations approval is separate from planning permission and covers structural safety, fire, insulation and drainage.
  • A structural engineer is normally needed before a contractor can price the job accurately.
  • Party Wall etc. Act 1996 notices must be served at least two months before work starts if you’re building near a shared boundary.
  • Site insurance and, for many projects, a structural warranty should be arranged before construction begins, not after.
  • Realistic timelines from approval to site start typically run 8 to 16 weeks, longer for listed buildings or large extensions.
  • The most common delays come from condition discharge, contractor availability, and late-appointed structural engineers.

Discharging Planning Conditions Before You Start

Most permissions come with conditions attached. Some are “pre-commencement” conditions, meaning you must discharge them before any work starts, including demolition or site clearance.

Typical pre-commencement conditions cover:

  • Materials samples
  • Landscaping details
  • Drainage and surface water strategy
  • Construction management plans (common on tighter London sites)

You apply to discharge conditions separately from your original planning application. Councils usually take 6 to 8 weeks to respond, so submit this early. Starting work before a pre-commencement condition is discharged can make the whole development unlawful, even though you have permission.

Photo 02 Edit01 2


Building Regulations Applications and Approval

Planning permission and Building Regulations approval are two different systems. Planning controls whether you can build; Building Regulations control how it’s built.

You’ll need Building Regulations sign-off for:

  • Structural stability
  • Fire safety and means of escape
  • Thermal insulation and energy performance
  • Drainage, ventilation and damp-proofing

You can apply through a Full Plans submission (checked before work starts) or Building Notice (checked as work progresses). For most extensions and conversions, Full Plans gives more certainty and fewer surprises on site.

Photo 03 Edit01 1

Appointing a Structural Engineer and Contractor

A structural engineer calculates beam sizes, foundation depths and load paths. Their calculations feed directly into your Building Regulations submission and your contractor’s price.

Appoint your engineer as soon as planning permission is granted, not after. Contractors can’t give an accurate quote without structural calculations, and delays here push your whole start date back.

When choosing a contractor:

  • Get at least three like-for-like quotes based on the same drawings
  • Check references from recent, comparable projects
  • Confirm their availability against your target start date, good contractors book up months ahead

Getting Detailed Construction Drawings Ready

Your planning drawings show what you’re allowed to build. They rarely contain enough detail for a contractor to build from.

Construction (technical) drawings add:

  • Precise dimensions and junction details
  • Specification of materials and fixings
  • Coordination with structural and services information

Skipping this stage is a common cause of on-site disputes and cost overruns, because pricing and workmanship both depend on clear, detailed information.

Photo 04 Edit01 1



Party Wall Agreements and Notices

If your work involves a shared wall, excavation near a neighbour’s foundations, or work on the boundary line, the Party Wall etc. Act 1996 applies.

  • Serve notice at least two months before starting work on the wall itself
  • One month’s notice applies for excavation-only works
  • If your neighbour dissents, a party wall surveyor is appointed to agree a Party Wall Award

This process runs alongside, not instead of, planning and Building Regulations. Leave it out of your programme and it can delay your start date significantly.

Arranging Site Insurance and Warranties

Standard household insurance often doesn’t cover building work. Before construction starts, arrange:

  • Contractor’s public liability insurance (ask for the certificate)
  • Site or works insurance covering the build itself
  • A structural warranty, particularly relevant for larger extensions, new builds or conversions, which protects you and future buyers

Mortgage lenders and future purchasers may ask for evidence of a warranty, so it’s worth arranging even if you don’t strictly need it now.

Photo 05 Edit01 1



Setting a Realistic Start Date

Work backwards from your ideal start date and build in time for:

  • Condition discharge (6 to 8 weeks)
  • Building Regulations approval (5 to 8 weeks for Full Plans)
  • Contractor procurement and mobilisation (4 to 8 weeks)
  • Party Wall process where relevant (1 to 2 months)

Several of these can run in parallel, but they all depend on having finished construction drawings and a structural engineer appointed early. Rushing this stage is the single biggest cause of slipped start dates.

What Can Delay the Start of Construction

  • Pre-commencement conditions not discharged in time, the most common and most serious delay
  • Contractor unavailability, especially if you start procurement too late
  • Late structural engineer appointment, holding up both drawings and quotes
  • Party Wall disputes, particularly where a neighbour dissents
  • Incomplete construction information, leading to price revisions once a contractor sees full detail
  • Material or product lead times, bespoke windows and structural steel can take months

At Extension Architecture, we manage this whole phase for our clients, from condition discharge through to contractor appointment, so the gap between approval and site start is as short and predictable as possible.

Photo 06 Edit01



Frequently Asked Questions about “What Happens Between Planning Approval and Construction? A Step-by-Step Timeline”

How long does it take to start construction after planning permission is granted? Typically 8 to 16 weeks, depending on how many conditions need discharging and how quickly you appoint a structural engineer and contractor. Listed buildings and larger schemes usually take longer.

Can I start work as soon as I get planning permission? Only if there are no pre-commencement conditions. If there are, starting work before they’re discharged can make your development unlawful, even with a valid permission.

Do I need Building Regulations approval if I already have planning permission? Yes. They’re separate systems. Planning permission allows the development; Building Regulations approval confirms it’s built safely and to the required technical standard.

When should I appoint a structural engineer? As soon as you have planning permission. Their calculations are needed for both your Building Regulations submission and an accurate contractor quote.

Do I need a Party Wall Agreement for an extension? If you’re building on or near a shared boundary, or excavating close to a neighbour’s foundations, yes. Notice must be served at least one to two months before work starts, depending on the type of work.

What’s the biggest cause of delay between approval and construction? Pre-commencement conditions not being discharged in time. This is the most common reason projects stall after permission is granted.

Img Nikki2

Nikki, Architectural Sales Consultant

Tell us about your plan and we'll send you a free quote! It takes less than 30 seconds!

Eugene Kim

Eugene Kim

Author

Eugene Kim, Founder and Managing Director of Extension Architecture, has led the firm for over 14 years, consistently delivering quality solutions. His dedication has been key to the company's growth and success.